Our teams, with maximum effort and dedication, are ensuring that the "Park Residence" Complex is being built at a fast pace and with high quality.
Here are some of our latest activities on-site:
Building 1 – Construction Block A18 (1-5)
• Reinforcement of the 9th-floor slab of the residential building.
Building 2 – Construction Block A18 (1-5)
• Installation of formwork and reinforcement of the frames at the base of the 5th floor of the residential building.
Building 10 – Construction Block A18 (9-13)
• Formwork of columns on the 4th and 5th floors of the residential building.
Building 11 – Construction Block A18 (9-13)
• Continuation of excavation work.
Building 12 – Construction Block A18 (9-13)
• Installation of formwork on the 1st floor of the residential building.
Building 13 – Construction Block A18 (9-13)
• Reinforcement of frames at the base of the -1 Underground level.
Every day we are one step closer to the completion of the giant Park Residence Complex. We thank all our teams for their work and dedication in bringing this project to life!
For more information, contact us:
044-458-458
0800 80 700
[email protected]
Or visit us at our sales offices.
We look forward to welcoming you!
Kompleksi Park Residence në Prishtinë, projekt nga Berisha Group po ...
Vetëm edhe pak ditë na ndajnë nga përfundimi i ofertës!Afati ...
Investo në të ardhmen tënde me Berisha Group! Blej banesë ...
Have you dreamed of owning a beautiful and modern apartment ...
The "N'SHESH" residential complex in the city of Viti is ...
In an extraordinary initiative for International Women's Day, Berisha Group ...